Line Diagram of division indicating Electrified & Non-Electrified Sections






































                                        Fig. Line Diagram of TRD SC Division

           a)     Details of Electrification during the year 2022-23 (Till date):

            Energisation particulars for the year 2022-23 (Till Date):


             Sl.N         Section/ Sidings             RKM        TKM       EIG No       Date          DOC
              o.

              1    BGSF-OPL                            19.9       27.7     2203085    23.03.2022    13.07.2022


              2    Rani & Others @ Sultanabad                     3.195    2210044    26.10.2022    27.10.2022


              3    Bhavanapalem to Sattupalli         14.251     14.251    2208026    22.08.2022     25.08.22


              4    SCCL/JVR-OC @ Sattupalli                        13      2208027    22.08.2022     25.08.22


              5    RKP-II Siding @ MCI                2.555       4.72     2208025    22.08.2022    27.08.2022


              6    Khanapur- Latur Road               98.57       112.6    2209035    24.09.2022    29.09.2022

                   CHERUV MADHAVARAM-
              7                                        5.52       5.52     2208027    16.08.2022    20.09.2022
                   KONDAPLLI
           Total 140.8 TKM has been electrified during the year.