Line Diagram of division indicating Electrified & Non-Electrified Sections
Fig. Line Diagram of TRD SC Division
a) Details of Electrification during the year 2022-23 (Till date):
Energisation particulars for the year 2022-23 (Till Date):
Sl.N Section/ Sidings RKM TKM EIG No Date DOC
o.
1 BGSF-OPL 19.9 27.7 2203085 23.03.2022 13.07.2022
2 Rani & Others @ Sultanabad 3.195 2210044 26.10.2022 27.10.2022
3 Bhavanapalem to Sattupalli 14.251 14.251 2208026 22.08.2022 25.08.22
4 SCCL/JVR-OC @ Sattupalli 13 2208027 22.08.2022 25.08.22
5 RKP-II Siding @ MCI 2.555 4.72 2208025 22.08.2022 27.08.2022
6 Khanapur- Latur Road 98.57 112.6 2209035 24.09.2022 29.09.2022
CHERUV MADHAVARAM-
7 5.52 5.52 2208027 16.08.2022 20.09.2022
KONDAPLLI
Total 140.8 TKM has been electrified during the year.