Page 120 - booklet draft
P. 120
cameras for each under progress.
OHE & PSI Depot (Memorandum of
sanction received on
20.10.2022)
Replacement of
Failure prone
3 27 20.17 7 Work Under Progress.
Contact wire
(NICCO make )
Enhancement of Work is executing by
Transformer Construction and in
capacity by 10 04 6 progress at DKJ (01),
4
adding the BDCR (02), GNP (02),
cooling fans VKB (01).
Provision of
5 RAILNET in all 12 0 12 Managing with dongle
depots.
Elimination of
Cross track feeder
for the first track LOA issued to M/s
by connecting
Mahalakshmi Enterprises
6 jumper directly 20 15 5 on 08.04.2022, Work
from gantry/ mast
using standard under progress.
out-rigger
arrangement.
Bonding of all
check rails, CMS
7 crossings and on 1 1 0 Work Completed
Bridges as per Spl.
Drive No. 55
One no. at 236/25-
27(BPA-ASAF section)
Conversion of - will be done in 3 rd line
11kV Power line account, One more at
8 crossings to UG 4 2 2 SKP-NPL Cable laying
crossing. completed Estimation of
Supervision charges
from EB is pending.
Conversion of Estimation of
33kV Power line Supervision charges
9 crossings with less 9 0 9 from EB is pending.
clearances to UG Details given in
crossing separate slide.