Page 125 - booklet draft
P. 125
Meters Equipment
tendering Commissioned Complet erection
13 Aler (ALER) TS
work under On 04.02.2020 ed work
progress completed
Meters Foundati
Ghatkesar tendering Commissioned Foundations
14 TS ons to be
(GT) work under On 21.04.2020 to be done
progress done
Meters Equipment
Sanathnag tendering Commissioned Complet erection
15 TS
ar (SNF) work under On 19.02.2020 ed work
progress completed
Meters Equipment
Vikarabad tendering Commissioned Complet erection
16 TS
(VKB) work under On 13.02.2020 ed work
progress completed
Tandur Meters Commissioned Complet Connection
17 TS
(TDU) Available On 13.03.2020 ed not given.
ABT meters
Malkhaid
18 Road KA Meters Commissioned Complet not
available on
ed
On 21.04.2020
Available
(MQR)
SEB side.
Equipment
ABT meters
KothaPalli Complet erection
19 TS not Available
(KHPI) ed work
available
completed
Mortad Meters Complet Work
20 TS Available
(MRTD) Available ed completed
WIRUR, KHNP traction sub-station has already been brought under Open
Access.
d) Good Works done by TRD/SC during the year 2022-23( Till oct 31st)
1. Network expansion:
Introduction of Electric traction on newly constructed BG 3rd line between BGSF-
OPL in KZJ-BPQ section (TKM: 19.9, RKM: 29.7KM):
As a part of patch tripling works between BPQ-KI section, the new 3rd
line between BGSF-OPL is charged on 13.07.2022, after attaining the
sanction vide letter No.E.220/TRD/PCEE RE Sanc/2022/02, dated:
13.07.2022.