Energisation of Private siding at M/s SCCl/JVR-OC at Sattupalli (TKM: 1.194, RKM:
0.994 KM):
The private siding M/s SSCI/JVR-OC at Sattupalli has been energized
and trail run conducted on 25.08.2022 after duly obtaining the EIG
sanction vide sanction no. 2208027, dated: 22.08.2022.
Fig: Charging of JVR-OC PVT Sdg. Fig: Electric Loco Trail Run
Energisation of 4&5 of RKP-II siding at MCI station (TKM: 4.72, RKM: 2.555 KM):
Energisation of newly lied OHE on Road 4&5 of RKP-II siding at MCI
station from OHE mast Loc. No. RKP II/4/1001A (Km.Ch.04/29.70) to
Loc. No.RKP II/6/18 (Km.Ch.06/585.0) done on 27.08.2022 after duly
obtaining the EIG vide sanction no. 2208025, dated: 22.08.22 and trail
run conducted.
Fig: Charging of 4 & 5 Lines of RKP-II Sdg At MCI.
Energisation of newly electrified BG line between KHNAPUR(Excl.)-LATUR (Incl.)
ROAD in VKB-PRLI section (RKM: 98.57, TKM: 112.60 KM):
As part of electrification works of single Broad Gauge(BG) line
between Vikarabad (VKB) – Parli Vaijnath(PRLI) of TKM: 313.86 (269
RKM), the section between Khanapur(KHNP), Latur Road(LTRR) of TKM
113 (98.6 RKM) has been commissioned on 29.09.2022 after duly
obtaining the EIG sanction vide statutory authorisation number 2209035.
With this 236.25 TKM (RKM: 203.81) of electrification has been completed
between VKB-PRLI.