Energisation of Private siding at M/s SCCl/JVR-OC at Sattupalli (TKM: 1.194, RKM:

                0.994 KM):
                The private siding M/s SSCI/JVR-OC at Sattupalli has been energized
                and trail run conducted on 25.08.2022 after duly obtaining the EIG

                sanction vide sanction no. 2208027, dated: 22.08.2022.















              Fig: Charging of JVR-OC PVT Sdg.                       Fig: Electric  Loco Trail Run


                Energisation of 4&5 of RKP-II siding at MCI station (TKM: 4.72, RKM: 2.555 KM):
               Energisation of newly lied OHE on Road 4&5 of RKP-II siding at MCI
               station  from  OHE  mast  Loc.  No.  RKP II/4/1001A  (Km.Ch.04/29.70)  to

               Loc. No.RKP  II/6/18  (Km.Ch.06/585.0)  done on  27.08.2022 after  duly
               obtaining the EIG vide sanction no.  2208025, dated: 22.08.22 and trail

               run conducted.

















                                Fig: Charging of 4 & 5 Lines of RKP-II Sdg At MCI.

           Energisation of newly electrified BG line between KHNAPUR(Excl.)-LATUR (Incl.)
           ROAD in VKB-PRLI section (RKM: 98.57, TKM: 112.60 KM):
                         As part of electrification works of single Broad Gauge(BG) line

           between Vikarabad (VKB) – Parli Vaijnath(PRLI) of TKM: 313.86 (269
           RKM), the section between Khanapur(KHNP), Latur Road(LTRR) of TKM

           113 (98.6 RKM) has been commissioned on 29.09.2022 after duly
           obtaining the EIG sanction vide statutory authorisation number 2209035.
           With this 236.25 TKM (RKM: 203.81) of electrification has been completed
           between VKB-PRLI.