P. 129

Charging of KKMP/SP @ PDPL-NZM section:

           After charging of MRTD/TSS in PDPL-NZB section, there is no SP for
           separation of supply between KPHI and MRTD TSS feeding. Now new SP
           has been constructed by RE department at KKMP and same was

           charged on 07.07.2022 after duly completing all the works and
           obtaining the EIG sanction vide sanction no.2207013, dated 05.07.2022.
           Previously feeding of Morthad TSS was extended up to KPHI feeding
           post.



















                                              Fig: Charging of KKMP/SP

                 Capacity enhancement of Traction Power transformers:
                  The  traction  Power  transformers  are  designed  with  dual  power
                 capacity  as  21.6  MVA  and  30.24  MVA  (Including  Colling  fans).
                 Maintaining the transformer temperature below a critical value by

                 proving  the  cooling  fans  enables  the  transformer  to  handle  a
                 designed enhanced load capacity of 30.24 MVA. The capacity of 04
                 numbers  of  traction  power  transformers  GNP-01(TR-83),  GT-02(TR-
                 73&74) and SNF-01 (TR-66) has been increased by commissioning the
                 cooling fans.



           .










                     Fig: Power Transformer (TR-83) with cooling fans at GNP Traction sub-station.

           2.     Through Enhancement works:




                Loop line isolation at LPI Station :
                       LPI Railway station became busiest railway station in the

           division and LPI became the starting/destination station for the most of
           the express trains in recent days. Getting power block for day to day
           maintenance of the OHE at LPI is very difficult even during the nights

           due to shunting and MMTS movement. Now Division has come up with