Fig: Dismantling of GL-7 at BPA


           3.     Reliability improvement works:


              OHE Modifications at AMQ due to shifting of point by Engg. Dept.:

                  Engineering department has planned the point shifting work (8 mts)

               at AMQ, for execution of the same, OHE Obligatory mast also to be

               relocated. TrD has done modifications accordingly by extending the
               turnout and relocation of the Obligatory mast.

















                                               Fig: Point shifting work at AMQ


               Provision of Disconnector assembly on top side of the Lightning Arrester (LA):
               As per revised SMI no. TI/SMI/0048

               (Rev.  1)  dated:  23.07.2021,  the
               Disconnector  assembly  of  LA

               should be repositioned at the Top
               of the LA. The Division has taken-

               up the work and replaced out all
                                                                                Fig: LA modification
               419 LAs modifications.




                Replacement of rusted ACC wire :

                        In polluted areas like SNF, KI, TDU and DKJ the anti-creep wires
               became rusted, due to this the mechanical strength of the wire got
               degraded. The snapping of which may leads to major breakdown. To