Page 133 - booklet draft
P. 133
Fig: ALU cat. Replacement work
Checking of OHE with 2032mm Pantograph:
As per the instructions from the Headquarters,
the checking of OHE with 2032 pantograph
completed in KZJ-BPQ, KZJ-SC, SC-WD, DKJ-KI
section in SC Division.
Fig: Checking of OHE
with 2032 mm in SC-WD .
4. Other Safety Improvement Works in train
operations:
Provision of Sigma Boards ahead of STOP Signals:
To assist Loco pilots for easily identifying the STOP
signals during foggy weather conditions,
Division has taken up the work of provision of
Retro reflective SIGMA boards, ahead of the
STOP signals. 44 no’s sigma boards were Fig: Sigma Board
provided.
Attention of Leaning/Critical implantation masts:
Leaning/critical implantation masts in OHE are the major concern
of panto entanglements and safely operation of trains with higher
speeds respectively in the Indian Railways. To avert all the problems due
to leaning/critical implantation masts total 44 locations eliminated in the
year 2022-23.
Fig: New mast erection at loc.279/17 Fig: New mast erection at loc. 279/13
Replacement of rusted Cantilever’s:
Rusted cantilevers are the one of the causes for breakdown in polluted
areas. Due to the rusting of the cantilever tubes, the mechanical