P. 133

Fig: ALU cat. Replacement work




                         Checking of OHE with 2032mm Pantograph:
               As per the instructions from the Headquarters,

               the  checking  of  OHE  with  2032  pantograph
               completed  in  KZJ-BPQ,  KZJ-SC,  SC-WD, DKJ-KI

               section in SC Division.
                                                                                        Fig: Checking of OHE
                                                                                      with 2032 mm in SC-WD .
           4.     Other Safety Improvement Works in train

                   operations:



                         Provision of Sigma Boards ahead of STOP Signals:
               To assist Loco pilots for easily identifying the STOP
               signals  during  foggy  weather  conditions,

               Division  has  taken  up  the  work  of  provision  of
               Retro  reflective  SIGMA  boards,  ahead  of  the

               STOP  signals.  44 no’s  sigma  boards  were                                Fig: Sigma Board
               provided.



                  Attention of Leaning/Critical implantation masts:
                  Leaning/critical implantation masts in OHE are the major concern
           of panto entanglements and safely operation of trains with higher

           speeds respectively in the Indian Railways. To avert all the problems due
           to leaning/critical implantation masts total 44 locations eliminated in the
           year 2022-23.



















                      Fig: New mast erection at loc.279/17               Fig: New mast erection at loc. 279/13

               Replacement of rusted Cantilever’s:

           Rusted cantilevers are the one of the causes for breakdown in polluted
           areas. Due to the rusting of the cantilever tubes, the mechanical