Page 137 - booklet draft
P. 137
4 Maintenance 0 0
5 Grid Failure 0 1
6 Miscellaneous 1 0
Total 2 2
h) Action Plan:
Action plan for block Burst cases:
Use of 100% Walkie talkies (License free) for better
communication among working staff.
Visit of site prior to block planning day.
Ensuring the T&P in Good condition.
Use of LED lights (360°)for the night working in tower car.
Aluminium Catenary wire replacement:
Total TKM Replaced 2017- 2018- 2019- 2020- 2021- 2022-23 Total
before 18 19 20 21 22 ( Till OCT 22)
2016-17
995 TKM 591.13 75 65.124 31.2 49 30.98 10.867 853.37
To be TKM TKM TKM TKM TKM TKM TKM
replaced
NICCO Contact wire replacement:
Total no Replace 2018-19 2019-20 2020-21 2021-22 2022-23 Balan
Tension d ( Till ce
lengths before OCT 22)
2018
Out of 407 2 TL 4 TL 41 TL 80 TL 42 TLs 16 TLs 185
TLs (2.755 (4.049 (53.013 (98.86 ( 53.47 (20.7 TLs
identified, TKMs) TKMs) TKMs) TKM) TKM) TKM)
197(
Identified in
trunk route)
TLs to be
replaced