Page 128 - booklet draft
P. 128
Fig: Speed trial commencement LTRR-KHNP Fig: Inspection of chamfer & hole in neutral Axis
Energisation of Patch tripling works between CHERUV MADHAVARAM(CVV)-
KONDAPLLI (KI) in KZJ-BZA section (TKM: 5.52, RKM: 5.52 KM):
As a part of patch tripling works between KI-BPQ, the section between
CVV-KI of 5.52 TKM/RKM IIIrd line (U/D) has been energized on
20.09.2022, after duly obtaining the EIG sanction vide sanction number
2208027, Dated:16.08.2022 & statutory CRS and EIG inspection.
Fig: Inspection of Neutral section @ loc. 565/22 Fig: Insp. & measurement of ATD parameters.
Energisation of Switching stations between KHNP-LTRR in VKB-PRLI section:
The energisation of switching stations (Halbarga/SSP, Bhalki/SSP,
Kamalnagar/SSP, Udgir/SSP and HER/SSP) in KHANAPUR (KHNP) – LATUR
ROAD (LTRR) BG Single line section of VKB-PRLI was done on 28.09.2022,
after duly obtaining the EIG sanction vide sanction number 2209036,
Dated:24.09.2022.
Fig: PCEE/EIG Statutory Inspection between KHNP-LTRR.