Fig: Speed trial commencement LTRR-KHNP          Fig: Inspection of chamfer & hole in neutral Axis


              Energisation of Patch tripling works between CHERUV MADHAVARAM(CVV)-
              KONDAPLLI (KI) in KZJ-BZA section (TKM: 5.52, RKM: 5.52 KM):
           As a part of patch tripling works between KI-BPQ, the section between
           CVV-KI of 5.52 TKM/RKM IIIrd line (U/D) has been energized on

           20.09.2022, after duly obtaining the EIG sanction vide sanction number
           2208027, Dated:16.08.2022 & statutory CRS and EIG inspection.

















           Fig: Inspection of Neutral section @ loc. 565/22   Fig: Insp. & measurement of ATD parameters.
              Energisation of Switching stations between KHNP-LTRR in VKB-PRLI section:
                      The energisation of switching stations (Halbarga/SSP, Bhalki/SSP,
           Kamalnagar/SSP, Udgir/SSP and HER/SSP) in KHANAPUR (KHNP) – LATUR
           ROAD (LTRR) BG Single line section of VKB-PRLI was done on 28.09.2022,

           after duly obtaining the EIG sanction vide sanction number 2209036,
           Dated:24.09.2022.
















                          Fig: PCEE/EIG Statutory Inspection between KHNP-LTRR.