Page 149 - ADMINISTRATIVE MANUAL
P. 149

149


                                           CHAPTER XIII. INFRASTRUCTURE
  ACTIVITY             BY CONTRACT                                             BY ADMINISTRATION
               OFFICE/UNIT  UNDERTAKING  OFFICE/UNIT                                      UNDERTAKING

                                                                 Approves sub-allotment for transmittal to the Accounting, Campus concerned


                                                                 Technical

   WORK AND    University Infra   Technical      University Infra   a.1 Determines the Scope of Work based on allocation
 FINANCIAL     Office                            Office          a.2 Prepares detailed Working Plans, Technical Specifications
 PLANS                         a.1 Determines the                a.3 Conducts Canvass/Survey on Construction Material Price
                               Scope of Work based               a.4 Prepares detailed Bill of Materials, Cost Estimates
                               on allocation                     a.5 Prepares Program of Work/PERT/CPM
                               a.2 Prepares detailed
                               Working Plans,                    Transmits to the President the Program of Work, Plans& Specification &
                               Technical                         Budgetary Ceiling
                               Specifications
                               a.3 Conducts                      Approves Program of Work, Plans & Specification & Budgetary Ceiling
                               Canvass/Survey on
                               Construction Material             Transmits to Campus Infra for pre-implementation activity in Exec. Director
                               Price                              coordination with the Head/Operating Unit.
                               a.4 Prepares detailed
                               Bill of Materials, Cost
                               Estimates
                               a.5 Prepares Program
                               of Work/PERT/CPM

                               Transmits to the
                               President the Program
               Office of the   of Work, Plans&   Office of the
               President       Specification &   President
                               Budgetary Ceiling

                               Approves Program of
                               Work, Plans &
                               Specification &
                               Budgetary Ceiling

                               Transmits to Univ.
                               Infra Office
                               requirement
                               preparation