Page 151 - ADMINISTRATIVE MANUAL
P. 151

151


                       Office of the President   Issues Notice of Award & require
                                          submission of Performance Bond

                                          Signs Contract

                                          Issues Notice to Commence Work

                       Board of Regents   2. Inform Board of Regent
                                          Issues Memorandum detailing
                                          Technical Staff of Univ. Infra Office      Issues Memorandum detailing one (1) Technical Staff
 PROJECT                                  at the Construction Site who shall       of the Campus Infra Office at the Campus where the
 INPLEMENTATION        Office of the President   be responsible in supervising the      project/s is/are undertaken who shall be responsible in supervising
 Supervision                              ongoing construction, to wit:   Office of the   the ongoing project/s, to wit:
                                                                     President   a.1 To see to it that the progress of work is in
                                          a.1 To see to it that the progress     accordance with the Work Program
                                          of work is in accordance with the      a.2 To see to it that the materials used are in
                                          Program of Work, Plans &               accordance with the plans and specification
                                          Specification.                         a.3 To regularly report to the ED through the Architect the progress
                                          a.2 To see to it that the materials    of work, copy furnished, President
                                          used are in accordance with the
                                          plans & specifications
                                          a.3 To initiate the issuance of
                                          certifications as to percentage of
                                          accomplishment in accordance
                                          with the Contract
       ACTIVITY                        BY CONTRACT                                         BY ADMINISTRATION
                          OFFICE/UNIT           UNDERTAKING          OFFICE/UNIT                    UNDERTAKING
                                          a.4 To submit all                      a.4 Note deviations or deficiencies & report the
                                          recommendations to the University      same to the ED and Campus Infra Office.
                                          President through the Univ. Infra
                                          Office and VP for Admin, copy
                                          furnished the Executive Director of
                                          the Operating Unit
                                          a.5 Call attention of Contractors or
                                          construction foreman of any
                                          deviation or deficiencies and
                                          report the same to the President
                                          through the Univ. Infra Office and
                                          VP for Admin.
                                          Issues Memorandum creating a
                                          Technical Review Team at the
                                          Central Administration, with the
                                          Exec. Director/Head of Operating
                                          Unit concerned as Chairman,
                                          which is tasked to review and
                                          confirm the recommendation of the
                                          Construction Supervisor and to
                                          submit to the President  a
                                          certification on all matters referred
                                          to the Team.
                                          Directs the Budget Office to
                                          release and/or prepare request for
                                          release of funding requirement in
                                          accordance with the percentage of
                                          accomplishment
                                          Releases funding to the Central
                                          Administration and/or prepares
                                          documents necessary to support
                                          release of funding warrant for the
                                          signature of the President

       ACTIVITY                        BY CONTRACT                                         BY ADMINISTRATION
                          OFFICE/UNIT           UNDERTAKING          OFFICE/UNIT                    UNDERTAKING
                                          Secures, if necessary, additional
                                          supporting documents from Univ.
                                          Infra Office and other Offices

                                          Submits to DBM request for
                                          release/s

                                          Follows up request/s when
                                          necessary

                                          Notifies the President upon
                                          release
   146   147   148   149   150   151   152   153   154   155   156