ACTIVITY                        BY CONTRACT                                          BY ADMINISTRATION
                           OFFICE/UNIT           UNDERTAKING           OFFICE/UNIT                     UNDERTAKING
                                                                                                      150
 PRE-IMPLEMENTATION    University Infra Office   Documentation       Executive Director/   Directs the Supply Office and End User

                                                                     Head, Operating   (Department concerned) to Canvass/Survey
                                           a.1 Undertakes reproduction of   Unit      Construction Material Prices
                                           Approved Program of Works,
                                           Plans, Specification &                     b. Directs the Campus Bids & Awards
                                           Budgetary Ceiling                          Committee in coordination with the Internal
                                           a.2 Provide copies of the                   Auditor to undertake the necessary steps in
                                           documents to concerned Offices             compliance with existing rules and regulations
                                           & PBAC                                     pertinent to bidding and award of supplies and
                                                                                       materials or pacquiao labor if applicable.


                                                                                      Evaluates Bid Proposals


                                                                                      Recommends awards to the ED/President/VP
                       PBAC                Pre-publication/advertisement   Campus Bids &   for Admin.
                                           meeting                   Awards Committee
                                                                                      Issue Purchase Order/Contract
                                           Meets the President to finalize
                                           time-table PERT/CPM
                                                                                      Inspect items delivered in the presence of the
                                           Prepares Public Bidding   Pres/VP/ED        End User
                                           Publication/Advertisement
                                                                                      Receives items delivered and issues the same
                                           Receives Pre-C1 documents   Internal        to the End User
                                           Conducts evaluation of Pre-C1   Auditor/Inspectors   Receives in accordance with the purposes for
                                           documents                                   which they are intended
                                           Recommends to the President   Supply Officer
                                           the contractors who will be
                                           allowed to participate in
                                           biddings/s & for inclusion in the   End User
                                           Role of Contractors of
                                           University, for approval

       ACTIVITY                        BY CONTRACT                                          BY ADMINISTRATION
                           OFFICE/UNIT           UNDERTAKING           OFFICE/UNIT                     UNDERTAKING

                                           Conducts Pre-Bid Conference

                                           Conducts Public Bidding

                                           Evaluates Bid Proposal/s to wit:

                                           i.1 Duly accomplished Proposal
                                           Form

                                           i.2 Authority of signatory

                                           i.3 Post C-2 duly notarized

                                           i.4 Detailed Cost Analysis

                                           i.5 Organization of the Project

                                           i.6 Site Inspection Certificate

                                           i.7 Affidavit that the Bid Bond is
                                           sufficient

                                           i.8 Bidder’s Bond
                                           i.9 PERT/CPM
                                           i.10  No.  of  calendar  days  to
                                           complete the project
                                           i.11 Bid Price
                                           Transmits  to  the  President  the
                                           complete  documents  of  the
                                           lowest  responsive  bidders,  and
                                           recommends  the  awarding  of
                                           contract

       ACTIVITY                        BY CONTRACT                                         BY ADMINISTRATION
                          OFFICE/UNIT           UNDERTAKING          OFFICE/UNIT                    UNDERTAKING

                       Board of Regents   Approves winning bidder

                                           Approves Contract