Page 39 - Presentation
P. 39

Among all tankages, this area is in


                     very bad condition by more water


                     stagnation and asphalt spillage.


                     The following has to be carried out


                     to overcome the same.



                     a.  Peripheral storm water canal


                            for  asphalt  tankage  shall  be

                            constructed at Road 9 North


                            side and asphalt tank farm east


                            side.



                     b.  Devegetation / asphalt removal


                            inside the dyke.


                     c.  Concreting of all asphalt tank


                            dykes               with             suitable                  slope


                            including                    dyke              canal              and


                            interconnection of the same


                            with peripheral canal.



                     d.  Road canal has to be constructed


                            on both sides for the road at

                            north side of tank farm after


                            elevation of the road.