11. Pipeline corridor:
a. Devegetation and removal of trees.
st
Action: Maint- Civil Target: 31 December -2021.
b. Ground clearance (300mm) and concreting of floor upto storm water canal with slope.
Action: Maint- Civil Target: 31 July -2022
st
c. Exclusive team for identification of redundant lines and submission of the report to Maint- Offsite for
removal of the same.
Action: OM&S / PE / Inspection Target: 31 August -2021.
st
d. Exclusive agency for stenciling / colour banding of all pipelines at clearly visible locations as per the
instruction by OM&S.
st
Action: OM&S / Maint- Offsite Target: 31 December -2021.