11.  Pipeline corridor:









































                          a.       Devegetation and removal of trees.




                                                                                                                                                st
                            Action: Maint- Civil                                                                               Target: 31  December -2021.


                          b.       Ground clearance (300mm) and concreting of floor upto storm water canal with slope.




                            Action: Maint- Civil                                                                               Target: 31  July -2022
                                                                                                                                                st


                          c.       Exclusive team for identification of redundant lines and submission of the report to Maint- Offsite for

                                   removal of the same.



                            Action:  OM&S / PE / Inspection                                                                    Target: 31  August -2021.
                                                                                                                                                st


                          d.       Exclusive agency for stenciling / colour banding of all pipelines at clearly visible locations as per the

                                   instruction by OM&S.



                                                                                                                                                st
                            Action:  OM&S / Maint- Offsite                                                                     Target: 31  December -2021.