ALDI – MASTER PLANNING
               The second year of planning focused on increasing their existing 230,000 sf campus to a projected
               410,000 sf total campus to support an employee increase from their existing 440 to an estimated
               830 employees. The proposed plan would include an additional office tower, specialty support
               spaces to include kitchens and sampling rooms and amenities such as a work café, auditorium
               and an elevated bridge to connect the new development to the north to the existing campus
               buildings.

               We hope to receive direction from the office of the presidents on the master plan and move into
               schematic design during the 2017 fiscal year.






















               WJE – JANNEY TECHNICAL CENTER (JTC)
               Another long-term client for whom FGM had previously completed an administrative renovation
               was  Wiss  Janney  Elstner.  FGM  was  asked  to  design  their  $22M  expansion  of  the  new  Janney
               Technical Center on their corporate campus. Design was completed in FY 2016 and construction
               began in the fall of 2016. The building consists of a variety of different lab spaces, offices and a
               large structural lab to support their consulting business. A new link to the existing building will be
               used as a gathering space and museum to display the company’s history.