Page 12 - FGMA_Corporate Office Renovation & Expansion - Architectural Design Services
P. 12

4.  ACKNOWLEDGE THE ACCEPTANCE OF EXHIBIT C – PROJECT SCOPE OF WORK ENCLOSED IN THIS
                   REQUEST FOR PROPOSAL. IF DESIGNER TAKES EXCEPTION TO ANY OF THE SERVICES THAT ARE
                   REQUESTED, IDENTIFY EXCEPTIONS AND PROVIDE A DETAILED EXPLANATION.

                FGMA acknowledges the acceptance of EXHIBIT C – Project Scope of Work enclosed in this
                Request for Proposal. We take no exception to any of the services that are requested.

                We do offer the following additions and clarifications as described below:

                Schematic Design (SD)
                9.    We believe the engineering disciplines should be introduced in this phase of the work.
                       This allows early feedback so that the design developed in this phase has some early
                       engineering design input.

                Design Development (DD)
                  5.    Engineering disciplines will be developed and coordinated into the deign process….
                  8.    Add…
                      •  Produce interior material and color palettes on sample boards
                  9.   Continue the weekly meetings in this phase and have a final design development
                        meeting at the end of this phase.

                Construction Documents (CD)
                  5.    Provide count of anticipated site visits required during the CD phase.
                     We believe 3 to 4 site visits may be required during this phase. FGMA may also request
                     site visits during the two prior phases so that we may verify any existing conditions during
                     the development of the design. Due to FGMA’s close proximity to the project site we
                     would not have any additional expenses for any potential visits.
                  6.    Prepare any early release bid packages that the team deems necessary to accommodate
                         the overall project schedule. These releases are included within our base proposal.
                  7.    FGMA would request that any consultant hired by AM King use REVIT as their
                         instrument of service. We work exclusively in REVIT and having the consultants in the
                         same program facilitates better document coordination and a smoother work flow. This
                         is especially important for MEP and Structural engineering.
                  8.    We would suggest at least 6 team meetings (one every other week) during this phase so
                         that questions and issues can be resolved by the entire team.