Page 18 - Magazine.cdr
P. 18
MOCKDRILLS
MOCK DRILL AT FGD RIHAND PROJECT
Emergency for which mock-drill is conduct: Fall of person from height
Type of mock-drill: Practice Drill
Overall response time: 30 mnts
Sr. No. Good points of mock drill Observed shortfall in mock drill
Workers (M/S KUNAL) called to site supervisor & Ambulance Driver & First Aider are not available
01
EHS person called to Ambulance. on vehicle. First aider had gone outside the plant
gate for petrol at the time of emergency.
Supervisor called to Bolero (M/S KUNAL) due to non Ambulance did not reach timely at
02 -availability of Ambulance. Supervisor and workers emergency location.
manually shifted the victim safely to the Bolero.
Corrective actions initiated related to observed
Sr. No. Responsibility Target
shortfall in mock drill, Area of improvement
Notified to Ambulance Driver and First aider Jaiprakash Gupta & Immediate after
01 regarding always be available to Ambulance &
Emergency. Notified to Ambulance driver and first Respective contractor mock drill
aider check the condition of Ambulance & fuel EHS
level (petrol) on regular basis.
16