Page 26 - LAGAN TEAMTALK AUTUMN 2019 FINAL VERSION
P. 26
LAI / LAM NEWS IRELAND WEST AIRPORT OFFICIALLY OPENED £10M SOUTHEND AIRPORT RUNWAY OVERLAY LAI / LAM NEWS
COMPLETED IN JUST 4 MONTHS
BY AN TAOISEACH, LEO VARADKAR
Lagan Airport Maintenance along with their JV partners Clare Civil Engineering have completed
works at Ireland West Airport in Knock, County Mayo. Lagan Airport Maintenance have delivered a £10 million Runway Overlay contract at Southend Airport in
a 4-month period on behalf of Stobart Rail & Civils. These works were to facilitate the arrival of Ryanair
operations at the airport.
The €11.2 million project included a complete resurfacing of
the existing of runway edge, centre line, and touch down zone
lighting ducting and other associated works.
These works were scheduled to ensure that the runway at
Ireland West Airport continued to meet the strict regulations
governing the operation and specification of runways at major
airports.
Runway 26/08, which opened in 1985 handles 100% of all
flights at the airport and this was the first time in its 34-year
history that the runway has had a full overlay.
This resurfacing works took place overnight outside of
operational hours over a 4-month period. This work could only
be undertaken at night as it required the full closure of the
airport’s main runway.
Speaking at the official opening of the runway on Friday 20 The 2,000-metre runway at Southend Airport was completely At the peak of the works 120 staff were on site and worked during
TEAMTALK : AUTUMN ‘19 project. millimetres of a combination of Marshall Asphalt Binder and Surface Other associated works included Airfield Ground Lighting, Drainage TEAMTALK : AUTUMN ‘19
September, An Taoiseach, Leo Varadkar, said: “Today’s
overlaid with Marshall Asphalt. In preparation the team planed off 50
strict night time possessions from 11pm to 5.30am with some
Pictured at Ireland West Airport for the official opening.
ceremony marks the successful completion of a truly ambitious
millimetres of the existing runway and overlaid the runway with 200
extensions agreed which were from 9pm to 6am.
Course.
“All of the work was done on time and on budget and I really
and Pit and Ducting Works.
want to acknowledge the work of the main contractors Lagan
Our in-house batching plants were erected on site and all works were
Aviation and Clare Civil Engineering, and also project partners
The team are pleased to report that they delivered the project
self-performed. During mobilisation of the batching plant the team
Atkins.”
sourced some materials externally to ensure production was not
throughout the duration of the works.
compromised. A total of 41,000 tonnes of Asphalt was laid throughout
the duration of the contract. within the required time-frame and had zero accidents or incidents
26 27