LAI / LAM NEWS  IRELAND WEST AIRPORT OFFICIALLY OPENED                                                                                                                 £10M SOUTHEND AIRPORT RUNWAY OVERLAY                                                                                                                                LAI / LAM NEWS

                                                                                                                                                                            COMPLETED IN JUST 4 MONTHS
           BY AN TAOISEACH, LEO VARADKAR



           Lagan Airport Maintenance along with their JV partners Clare Civil Engineering have completed
           works at Ireland West Airport in Knock, County Mayo.                                                                                                             Lagan Airport Maintenance have delivered a £10 million Runway Overlay contract at Southend Airport in
                                                                                                                                                                            a 4-month period on behalf of Stobart Rail & Civils.  These works were to facilitate the arrival of Ryanair
                                                                                                                                                                            operations at the airport.

                                                                                                   The €11.2 million project included a complete resurfacing of
                                                                                                   the existing of runway edge, centre line, and touch down zone
                                                                                                   lighting ducting and other associated works.

                                                                                                   These works were scheduled to ensure that the runway at
                                                                                                   Ireland West Airport continued to meet the strict regulations
                                                                                                   governing the operation and specification of runways at major
                                                                                                   airports.

                                                                                                   Runway 26/08, which opened in 1985 handles 100% of all
                                                                                                   flights at the airport and this was the first time in its 34-year
                                                                                                   history that the runway has had a full overlay.

                                                                                                   This resurfacing works took place overnight outside of
                                                                                                   operational hours over a 4-month period.  This work could only
                                                                                                   be undertaken at night as it required the full closure of the
                                                                                                   airport’s main runway.

                                                                                                   Speaking at the official opening of the runway on Friday 20              The 2,000-metre runway at Southend Airport was completely                        At the peak of the works 120 staff were on site and worked during
     TEAMTALK : AUTUMN ‘19                                                                         project.                                                                 millimetres of a combination of Marshall Asphalt Binder and Surface              Other associated works included Airfield Ground Lighting, Drainage                 TEAMTALK : AUTUMN ‘19
                                                                                                   September, An Taoiseach, Leo Varadkar, said: “Today’s
                                                                                                                                                                            overlaid with Marshall Asphalt.  In preparation the team planed off 50
                                                                                                                                                                                                                                                             strict night time possessions from 11pm to 5.30am with some
          Pictured at Ireland West Airport for the official opening.
                                                                                                   ceremony marks the successful completion of a truly ambitious
                                                                                                                                                                            millimetres of the existing runway and overlaid the runway with 200
                                                                                                                                                                                                                                                             extensions agreed which were from 9pm to 6am.
                                                                                                                                                                            Course.
                                                                                                   “All of the work was done on time and on budget and I really
                                                                                                                                                                                                                                                             and Pit and Ducting Works.
                                                                                                   want to acknowledge the work of the main contractors Lagan
                                                                                                                                                                            Our in-house batching plants were erected on site and all works were
                                                                                                   Aviation and Clare Civil Engineering, and also project partners
                                                                                                                                                                                                                                                             The team are pleased to report that they delivered the project
                                                                                                                                                                            self-performed.  During mobilisation of the batching plant the team
                                                                                                   Atkins.”
                                                                                                                                                                            sourced some materials externally to ensure production was not
                                                                                                                                                                                                                                                             throughout the duration of the works.
                                                                                                                                                                            compromised.  A total of 41,000 tonnes of Asphalt was laid throughout
                                                                                                                                                                            the duration of the contract.                                                    within the required time-frame and had zero accidents or incidents
  26                                                                                                                                                                                                                                                                                                                                         27