21.5.4 Independent
Construct BLACK WATER holding tank vents so they are independent of all
other tanks.
Construct wastewater holding tank vents so they are independent of all sanitary
water tanks. Wastewater tank vents can be combined with each other.
21.5.5 Reuse of Treated Black and Gray Water
VSP will assess water reuse systems during plan reviews.
21.6 General Hygiene
Construct handwashing stations in the following areas according to section 7.1.
21.6.1 Wastewater Areas
Install at least one handwashing station in each main wastewater treatment,
processing, and storage area.
21.6.2 Laundry Areas
Install at least one handwashing station in soiled linen handling areas and at the
main exits of the main laundry. Vessel owners will provide locations during the
plan review.
21.6.3 Housekeeping Areas
Install handwashing stations in housekeeping areas as described in section 35.1.
Provide each handwashing station with a soap dispenser, paper towel dispenser,
waste receptacle, and sign that states “wash hands often,” “wash hands
frequently,” or similar wording in English and in other languages, where
appropriate.
22.0 Potable Water System
22.1 Striping
22.1.1 Potable Water Lines
Stripe or paint POTABLE WATER lines either in accordance with ISO 14726
(blue/green/blue) or in blue only.
22.1.2 Distillate and Permeate Water Lines
Stripe or paint DISTILLATE and PERMEATE WATER LINES directed to the
POTABLE WATER system in accordance with ISO 14726 (blue/gray/blue).
22.1.3 Other Piping
No other lines should have the color designations listed in 22.1.1 or 22.1.2.