Page 164 - Operations Strategy
P. 164

CAPACiTy CHAngE  139
                             operation where forecast demand is increasing seeks to satisfy all demand by increas-
                             ing capacity using large capacity increments, it will have substantial amounts of over-
                             capacity for much of the period when demand is increasing, which results in higher
                             unit costs. However, if the company uses smaller increments, although there will still be
                             some over-capacity it will be less than that using large capacity increments. This results
                             in higher-capacity utilisation and therefore lower costs. Remember, though, that the
                             larger increments of capacity can be intrinsically more efficient (because of economies
                             of scale) when they are well utilised. For example, suppose that the air conditioning
                             unit manufacturer forecasts demand increase over the next three years, as shown in
                             Figure 4.9(a), to level off at around 2,400 units a week. If the company seeks to satisfy
                             all demand by building three plants, each of 800 units’ capacity, the company will
                             have substantial amounts of over-capacity for much of the period when demand is
                             increasing. Over-capacity means low-capacity utilisation, which in turn means higher
                             unit costs. If the company builds smaller plants, say 400-unit plants, there will still be
                             over-capacity but to a lesser extent, which means higher-capacity utilisation and pos-
                             sible lower costs.

                             Risks of over-capacity with large capacity increments
                             The inherent risks of changing capacity using large increments can also be high. For
                             example, if the rate-of-change of demand unexpectedly slows, the capacity will be only
                             partly utilised. However, if smaller units of capacity are used the likelihood is that the
                             forecast error would have been detected in time to delay or cancel the capacity adjust-
                             ment, leaving demand and capacity in balance. For example, if demand does not reach
                             2,400 units a week but levels off at 2,000 units a week, the final 800-unit plant will
                             only be 50 per cent utilised. However, if 400-unit plants are used the likelihood is that
                             the over-optimistic forecast would have been detected in time. Figure 4.9(b) shows the
                             consequences of adopting each of the two strategies in this case.





                   Figure 4.9  (a) Capacity plans for meeting demand using either 800- or 400-unit capacity plants
                   and (b) smaller-scale capacity increments allow the capacity plan to be adjusted to accommodate
                   changes in demand

                                         Capacity plan using                  Capacity plan using
                                           800-unit plants                      800-unit plants
                                 Capacity                             Capacity
                        2,400   plan using                   2,400   plan using
                                                                                       Forecast demand
                                 400-unit        Demand      2,000    400-unit      Actual demand
                       Volume (units/week)  1,600           Volume (units/week)  1,600
                        2,000
                                  plants
                                                                       plants
                        1,200
                                                             1,200
                         800
                                                              400
                         400                                  800

                                         Time                                 Time
                                         (a)                                  (b)










        M04 Operations Strategy 62492.indd   139                                                      02/03/2017   13:02
   159   160   161   162   163   164   165   166   167   168   169