Page 170 - BASIC GUIDELINE FOR QS
P. 170

Professional Practice: Guideline for Quantity Surveyor                                                     Chapter 5



                   5.8.14  Prime Cost Sum

                   A prime cost sum or PC sum is an allowance, usually calculated by the cost consultant,
                   for  the supply of work or materials to  be  provided  by  a contractor or supplier that  will
                   be nominated by  the client (that  is,  a supplier that  is  selected  by  the client to  carry  out

                   an element of   the works and    imposed    on   the main   contractor after   the main
                   contractor has been appointed).

                          The allowance is exclusive of any profit mark up or attendance (such as material
                   handling, scaffolding and rubbish clearance, etc.) by the main contractor.
                          Payments are  made  based  on  the quotations/invoices of  the supplied items  by

                   the contractor plus   addition   of   reasonable/agreed    percentages    for overhead
                   costs and profits.   If   the contractor's actual cost is   higher   than   the bill   of

                   quantities allowance,  then  the contract  sum will  be  increased  to  balance  it  up  and  if
                   the cost to the contractor is lower, then the contract sum will be reduced by the balance.
                          The contractor should  make  reasonable  provisions  within  their price for prime

                   cost  sums,  however,  these  can  prove  inadequate,  and  so prime  cost  sums can  be  a
                   source of increased costs and disputes.



































                                           Figure 5.17: Sample of Prime Cost Sum



                                                             159
   165   166   167   168   169   170   171   172   173   174   175