Page 13 - Charter School Brochure
P. 13

Overview
                                                                               Project References
            Phase I – Elementary School Addition                               Owner
            A new 2-story, 15,000 SF addition to the existing high school at 90 Rock Street.   Jim Dowd
            Space included the development of 5 kindergarten classrooms on Level 2 and 5   c/o Skanska USA Building
            first grade classrooms on Level 1. Alterations within the existing building took   KIPP Lynn Fund, Inc.
            place as well on both levels and consisted of relocating offices and breakout   617-466-5110
            rooms to facilitate corridor connections to the addition. Additionally, this
            phase included a new parking lot, basketball court and two synthetic turf fields   Designer
            among other site improvements and landscaping. The high school remained   Kathryn Dorman Ferrier
            fully occupied and operational throughout construction of this phase.      Architect
                                                                               Arrowstreet, Inc.
            Phase II – New High School Renovation                              617-666-7009
            Conversion of a 100-year-old warehouse building into a new modern-day high
                                                                               OPM
            school.  The existing loading dock is being transformed into a new, multilevel
                                                                               Mary Ann Williams
            dining commons featuring a glass storefront overlooking the street.
                                                                               Project Executive
                                                                               Skanska USA Building
            Highlights and Challenges                                          617-574-1463

            Some of the project’s highlights and challenges included:

            Phase I
                   •  Phase I was completed within a fast-track, 8 month schedule. Our team utilized early packages for utilities, foundation,
                    steel, rough-in and finishes, sitework and landscaping.  All work was performed during the 2016 school year and
                    turned over for the start of the 2017 school year.

                   •  Coordination and communication with the school was critical to the success of Phase I. KIPP was fully occupied for
                    about 95% of the project. We shared a parking lot and coordinated around all school activities including drop-off,
                    recess and pick-up. Selected scope involved connection to the existing school via corridors as well as MEP’s.

            Phase II
                   •  The existing building was purchased outright by KIPP during partial occupancy. Heavy demolition scope was
                    required and performed off-shift as to not disturb KIPP in Building B and one remaining daycare tenant in Building
                    A. Throughout demolition additional scope was required including extensive flooring underlayment removal.

                   •   The project faced a complex phasing schedule in which MEP and life systems had to be maintained throughout the
                    school year. Many upstream or downstream “out-of-phase” systems had to be identified and addressed (i.e., replaced,
                    modified or relocated) to meet the needs of the occupied school. Such work was performed on second shift to
                    avoid disturbance in occupied areas. Ongoing maintenance and troubleshooting of the combined fire alarm system
                    servicing the existing school and construction is one example of this challenge. Other phasing challenges included
                    building access, egress and stairwells.

                   •  The front office reception area could only be renovated outside of the academic school year, as this served as the main
                    building lobby during occupancy. Thus, the project included an intensive summer work phase during which W.T.
                    Rich renovated and tied in integral life safety and building systems.

                   •  Due to the inherent complex nature of the project and existing conditions of the building, there were numerous hidden
                    conditions that needed to be accounted for as the work progressed. W.T. Rich was able to respond to these issues
                    effectively and ensure that competitive pricing was obtained from contractors, and that changes were implemented
                    without the need for a time extension on any phases.
            Results


            W.T. Rich successfully completed Phase I on-time, within budget, and is on target for Phase II.


                                                W
                                                W.T. Rich Company, Inc. .T. Rich Company, Inc.
                                                                                                          Page | 11age | 11
                                                                                                          P
   8   9   10   11   12   13   14   15   16   17   18