Page 29 - COLLAGE
P. 29

5. CHAPTER



                                       CONSTRUCTION AND MAINTENACE



                    5.1.  CONSTRUTION


                    The first stage of the SR 520 floating bridge replacement project was the construction of

                    77 concrete pontoons in 2011 and 2012 by Kiewit-General-Manson at two purpose-built
                    facilities  in  Aberdeen  and  Tacoma.  The  pontoons  were  floated  to  the  bridge  on  Lake

                    Washington via the Lake Washington Ship Canal. Pontoon assembly and fastening, to
                    form the floating bridge's deck, began in 2014 and concluded in July 2015.


                    In 2012, WSDOT identified cracks and other problems with the first batch of completed
                    pontoons, estimating that it would cost $400 million to repair cracks and other flaws that

                    would bring down the bridge's predicted lifespan below the desired 75 years. The problems

                    stemmed from shortcuts allegedly taken by contractors to complete pontoons to meet set
                    deadlines; the proposed solutions to fix the pontoons included adding high-tension steel

                    cables and post-tensioning of the concrete.A floating, 660-short-ton (600 t) cofferdam was
                    launched  in  November  2013  to  assist  in  repairs  of  the  pontoons,  functioning  as  a

                    portable dry-dock that wrapped around parts of the pontoons. The repairs were made by
                    contractors from December 2013 to June 2014 and cost a total of approximately $208

                    million, using up the majority of the program's reserve funds. As a result of the pontoon

                    issues, the estimated opening of the bridge was pushed back from December 2014 into
                    2016.


                    Construction of the bridge deck, beginning with the eastern approach in Medina, began in
                    March 2012.


                    In  March  2015,  two  construction  accidents  on  the  bridge  slowed  construction  for
                    revaluation of safety measures: a contractor was killed after a high fall on the east high

                    rise  and  a  crane-lifted  load  of  steel  pipes  swung  out  of  control  into  a  King  County
                    Metro bus and an overhead highway sign.


                    The bridge deck was lifted into place in August 2015, and the final concrete pour was
                    finished in October 2015, completing the bridge deck.




                                                           29
   24   25   26   27   28   29   30   31   32   33   34