5. Which of these activities occur during the Planning phase? Choose three.
A. High-level scope definition
B. Budget
C. Business case
D. Schedule
E. Change control
F. Resources
6. The Closing phase addresses which of the following? Choose three.
A. Project sign-off
B. Lessons learned
C. Governance processes
D. Change control closeout
E. Integration plan is put into place.
F. Deliverables verification
7. Which of the following options are processes in the project management process
groups? Choose three.
A. Risk
B. Initiating
C. Monitoring and Controlling
D. Procurement
E. Scope
F. Planning
8. This phase is where the work of the project is performed.
A. Planning
B. Monitoring and Controlling
C. Initiating
D. Executing
9. Which of the following is true concerning the project charter?
A. Describes the project schedule
B. Contains cost estimates for each task
C. Authorizes the start of the project work
109