Page 112 - Project+
P. 112

A.  Project team actions are dictated.


         B.  It may regard budget, resources, or schedule.

         C.  Project team actions are restricted.

         D.  Project situations are believed to be true.

    19.  This component of the project charter describes the characteristics of the product of
         the project.

         A.  Milestones

         B.  Deliverables

         C.  Project description

         D.  Goals and objectives

   20.  Your project is to be performed outdoors. You are only four days from the big event,

         and there is a hurricane headed for shore. This is an example of which of the
         following?

         A.  Risk

         B.  Assumption

         C.  Deliverable

         D.  Constraint
















































                                                            112
   107   108   109   110   111   112   113   114   115   116   117