D.  Lists the responsibilities of the project selection committee


    10.  Which of the following is performed once the project charter is signed?

         A.  You should hold a project kickoff meeting.

         B.  You should write the project scope statement.

         C.  You should submit the request and the project charter to the project selection
              committee.

         D.  You should develop the project schedule.

    11.  You have just defined the major events for the project that will be used to
         determine and measure checkpoints throughout the project and determine whether

         the project is on time. What are they?

         A.  Deliverables

         B.  Goals

         C.  Milestones

         D.  Tasks

    12.  Your project sponsor has just signed the project charter. You held the kickoff
         meeting, and everyone on the team is anxious to get started on the work of the
         project. You are having a tough time holding them back and tell them you need to

         develop the work breakdown structure, schedule, and communication plan as a
         start. Which of the following is true regarding this scenario?

         A.  You’ve just completed the Initiating process.

         B.  Your team wants to jump right to the Executing process.

         C.  The next step in the project lifecycle is to begin the Planning process group.

         D.  The project sponsor has approved resources and funding for the project.

         E.  All of the above.

    13.  Identify the items that should not be included in a project charter. Choose three.

         A.  High-level budget

         B.  Project objectives


         C.  High-level cost-benefit analysis

         D.  Equipment and resources needed

         E.  Business case

         F.  Project description

         G.  High-level list of risks