Page 157 - Project+
P. 157

7               Determine office placements.                     Tasks 1–3
        8               Determine printer locations.                     Tasks 1–2

        9               Determine breakroom areas.                       Tasks 1, 2 and “Interior
                                                                         Designer” deliverable

        10              Seating chart drafts to managers.                Tasks 1–9

        11              Functional managers review seating Task 10
                        chart drafts.

        12              Final seating chart approved.                    Task 11


       You need to determine some rough order-of-magnitude estimates for these tasks
       to determine start and end dates. For example, based on the recommendation
       from the functional managers that the final seating chart be approved before the
       cube buildouts begin, you know that Task 12 must finish before you place the order
       for the cubicle furnishings.

       When breaking down the tasks for the “Procure and install cubicle furnishings”
       deliverable and determining start and finish dates, you realize you are working

       with a constraint that requires all cubicles and office furniture be delivered and
       installed by December 31. When you met with the IT director shortly after the
       scope statement was written, you discovered two weeks are needed to place
       computer equipment, monitors, and telephones on each desk. The cubicle
       buildouts and furniture delivery are predecessors to the computer equipment

       setup deliverable, so you need to determine when the cubicle furnishing order
       should be placed.

       You’ve obtained an estimate from a vendor that it takes roughly two days to install
       250 cubicles. Based on assumptions you’ve made in your conversations with Kate
       and the two functional managers who helped develop the task list, you think there
       will be a minimum of 1,000 cubicles. To allow IT two weeks to install the computer
       equipment, you determine delivery of the cubicle materials must occur by

       December 6. Cubicle buildouts can begin December 7 and must finish by
       December 15 (taking into account weekend days).

       In summary, your cubicle furnishing order will take six weeks to fill according to
       your vendor contacts. If the materials must be delivered no later than December 6,
       that means Task 12 from the “Survey the Main Street Office Building” deliverable
       has to finish by October 25. You can work backward from October 25 to determine
       the start and end dates for each task in this deliverable.

       You continue breaking down each deliverable into a list of tasks, sequence them in

       the proper order, determine start and end dates, and assign resources to the tasks
       to come up with the final schedule.

       On the project schedule, you also add two quality gates: one after the general
       contractor has completed the floor remodels and one after the cubicles are built.



                                                            157
   152   153   154   155   156   157   158   159   160   161   162