     9.  Activity B on your project schedule starts on Monday, October 3, and ends on
         Wednesday, October 12. You calculate duration in workdays, and the team does not
         work on Saturdays or Sundays. How many days is the total duration of this task in
         workdays?

         A.  9 days

         B.  10 days


         C.  8 days

              D. 7 days

    10.  Which of the following is not true for critical path tasks?

         A.  The early start date is less than the late start date.

         B.  These activities are on the longest full path on the project schedule.

         C.  The float time for tasks is zero.

         D.  The late finish date is the same as the early finish date.

    11.  Starting two activities at the same time that were previously scheduled to start
         sequentially is known as which of the following?

         A.  Fast tracking


         B.  Mandatory dependency

         C.  Crashing

         D.  Baselining

    12.  Your task requires 4 miles of paving, and it will take 30 hours to complete a mile.
         On a past project similar to this one, it took 150 hours to complete. Which of the
         following is true regarding this estimate?

         A.  The total estimate for this task is 120 hours, which was derived using expert
              judgment.


         B.  The total estimate for this task is 120 hours, which was derived using parametric
              estimating.

         C.  The total estimate for this task is 150 hours, which was derived using analogous
              estimating.

         D.  The total estimate for this task is 150 hours, which was derived using expert
              judgment.