13. Governance gates include all of the following except for which one?
A. Assigning a go/no-go decision point
B. Obtaining client sign-off
C. Securing management approvals
D. Obtaining legislative approvals
E. Assuring the work is performed correctly
14. You’re working on a project that you and your team have estimated takes 15
business days to complete. Your team does not work on Saturday, Sunday, or
holidays. Given the work calendar shown here and a start date of Tuesday,
November 1, what is the scheduled completion date for this task?
Sun Mon Tue Wed Thu Fri Sat
1 2 3 4 5
6 7 8 9 10 11 Holiday 12
13 14 15 16 17 18 19
20 21 22 23 24 Holiday 25 26
27 28 29 30
A. 21
B. 15
C. 22
D. 23
15. All of the following are true regarding milestone charts except for which one?
A. Milestone charts list the major deliverables or phases of a project.
B. Milestone charts show the scheduled completion dates.
C. Milestone charts show the actual completion dates.
D. Milestone charts are commonly displayed in bar chart format.
16. You’re in the process of developing a project schedule for a new project. You’ve just
completed the WBS. What would be the project manager’s next step in figuring out
what tasks go into the project schedule?
A. Develop a task list.
B. Determine the critical path tasks.
C. Develop a project schedule.