3.  What is analogous estimating also referred to as?


         A.  Bottom-up estimating

         B.  Expert judgment

         C.  Parametric estimating

              D. Top-down estimating

     4.  You are working on your network diagram. Activity A is a predecessor to Activity B.
         Activity B cannot begin until Activity A is completed. What is this telling you?

         A.  There is a mandatory dependency between Activity A and Activity B.

         B.  There is a finish-to-start dependency relationship between Activity A and
              Activity B.


         C.  Activity A and Activity B are both on the critical path.

              D. Activity B is a successor to multiple tasks.

     5.  What are the most commonly used forms to display project schedules? Choose two.

         A.  PERT charts

         B.  Gantt charts

         C.  CPM diagrams

              D. A spreadsheet

     6.  What are the crashing and fast tracking techniques used for?

         A.  Duration compression

         B.  Activity sequencing

         C.  Precedence diagramming


              D. Task definition

     7.  Which of the following is true for float?

         A.  It’s calculated by adding the durations of all tasks and dividing by the number of
              tasks.

         B.  It’s time that you add to the project schedule to provide a buffer or contingency.

         C.  It’s the amount of time an activity can be delayed without delaying the project
              completion date.

              D. It is calculated only on the longest path of the project schedule.

     8.  You have added a checkpoint in the project schedule to determine whether the

         work is accurate. What is this called?

         A.  Governance gate