D.  Estimate activity duration.


    17.  After the schedule is approved by the sponsor, customer, and key stakeholders,
         what happens next?

         A.  The resources are assigned.

         B.  The schedule baseline is established.

         C.  The task start and end dates are finalized.

         D.  The critical path is finalized.

    18.  Which is the most commonly used logical relationship?

         A.  Finish-to-start

         B.  Start-to-finish

         C.  Start-to-start


         D.  Finish-to-finish

    19.  How long is the critical path in days in the graphic shown here if you eliminate Task
         B?


























         A.  13 days

         B.  20 days

         C.  27 days

         D.  30 days

   20.  The following exhibit shows a series of tasks in a project schedule. Which path
         represents the critical path?