Gantt chart
         governance gates


         internal dependency

         logical relationship

         mandatory dependency

         network diagram

         parametric estimating

         precedence diagramming method (PDM)

         predecessor

         Program Evaluation and Review Technique (PERT)

         quality gates


         resource calendar

         schedule baseline

         sequencing

         successor

         task list

         top-down estimating



     Review Questions


     1.  Which of the following is not true for the critical path?

         A.  It has zero float.

         B.  It’s the shortest activity sequence in the network.


         C.  You can determine which tasks can start late without impacting the project end
              date.

         D.  It controls the project finish date.

     2.  You are a project manager for a major movie studio. You need to schedule a shoot
         in Denver during ski season. This is an example of which of the following?

         A.  External dependency

         B.  Finish-to-start relationship

         C.  Mandatory dependency

              D. Discretionary dependency