Page 199 - Project+
P. 199

Now that you have the resource requirements, the work effort estimates, and the rate

     for each task, you can complete the cost estimate by adding a Total Cost column to the
     table. The cost of each task is calculated by multiplying the work effort for each
     resource by the rate for that resource. This will give you the total project cost estimate.
     Table 7.2 shows a completed cost estimate for the tasks in the sample project.


     TABLE 7.2 Sample project cost estimate

                       Task Resource                Work Effort Rate                  Total Cost

                       4.1.1    Tech writer         20 hours           $30/hr         $600

                       4.1.2 Programmers 100 hours                     $150/hr        $15,000
                       4.1.3 Server                 Fixed rate         $100,000 $100,000

                       4.1.4 Testers                60 hours           $80/hr         $4,800

                       4.1.5 Programmer 200 hours                      $150/hr        $30,000

                       4.1.6 Marketing              30 hours           $60/hr         $1,800

                       Total                                                          $152,200


     Three-Point Estimates

     Three-point estimates are an average of the most likely estimate, the optimistic
     estimate, and the pessimistic estimate. You should ask team members and/or ask

     subject-matter experts who are familiar with this type of purchase or consulting work
     to give you estimates. They should base these on their past experience with similar
     work or their best guess based on their expertise.

     The most likely estimate assumes that costs will come in as expected. If you are using
     this to estimate activity durations, this estimate assumes work proceeds according to
     plan, that there won’t be any obstacles, and that the team member is confident they

     have the skills to complete the task.
     The optimistic estimate is an estimate that is better than expected. For example, you

     may have estimated internally that the consulting work you are requesting will be $225
     per hour. The optimistic estimate might be $212 per hour, which is better than what
     you expected. If you are using this estimate for activity duration, this estimate is the
     fastest time frame in which your resources can complete the activity. This might
     assume that other tasks the resource is working on are completed early or no longer

     need to be worked on during the same time frame as the current task. It could also
     mean that the work is easier than anticipated so the task could complete early.

     The pessimistic estimate assumes the goods or services will cost more than expected. If
     you are using this for activity duration, it assumes the work will take longer than
     anticipated to complete or that obstacles will crop up along the way that will delay
     completing the work.

     Calculating the three-point estimate is straightforward. It’s an average of the sum of



                                                            199
   194   195   196   197   198   199   200   201   202   203   204