Page 200 - Project+
P. 200

the estimates. For example, let’s say your most likely estimate is $120 per hour. The

     optimistic estimate is $110 per hour, and the pessimistic estimate is $150 per hour. The
     three-point estimate is calculated this way:

     ($120 + $110 + $150) / 3 = $126.67 per hour

     The three-point estimate for this work is $126.67 per hour. This estimate is only as
     good as the estimates given for the three points in the calculation. This estimate can
     swing between accurate and poor based on the quality of the estimates provided by the

     subject-matter experts.





                   Most of the estimating techniques discussed in this section can also be
       used to determine the task durations on the project schedule.




     Estimating Tips

     Cost estimating can be complex, and cost estimates often turn into the official cost of
     the project before you have the proper level of detail. You will probably never have all
     the information that you’d like when calculating cost estimates, but that’s the nature of

     project management. Here are some thoughts to keep in mind as you work through the
     estimating process:

     Brainstorm with your project team. Work with your team and other subject-
     matter experts to make certain you’ve accounted for cost estimates that may not be so
     obvious. For example, do any of your project team members require special training in
     order to perform their duties on the project? Are there travel costs involved for team
     members or consultants? Getting the team together to talk about other possible costs is

     a good way to catch these items.

     Communicate the type of estimate you are providing. Make certain your
     stakeholders are aware of the types of estimates you’re using and the level of accuracy
     they provide. If you’re preparing an analogous estimate based on a similar project, be
     up front regarding the possibility of this estimate deviating from the actual cost of the
     project.






                In addition to emphasizing the potential inaccuracies of an analogous
       estimate, provide stakeholders with a timeline for a definitive estimate. A project
       sponsor is more willing to accept that your current estimate may be lower than the
       actual cost of the project if they understand why the current estimate is vague and
       what is being done to provide a more accurate estimate.



     Make use of any available templates. Many companies have cost-estimating




                                                            200
   195   196   197   198   199   200   201   202   203   204   205