Page 198 - Project+
P. 198

techniques, but they’re also the most time-consuming to perform.



     When I discussed schedule planning in Chapter 5, I talked about calculating duration

     estimates for each task to determine the length of time your project will take. When
     you are calculating cost estimates, you need to base the estimate on work effort, which
     is the total time it will take for a person to complete the task if they do nothing else
     from the time they start until the task is complete. For example, assume a task to
     perform technical writing has an activity duration estimate of four days. When you
     perform cost planning, you need to know the actual number of hours spent performing
     the task. So, let’s say the technical writer is allocating 5 hours a day to the project over

     the course of 4 days. The work effort estimate is 5 hours a day multiplied by 4 days,
     which equals 20 hours.





                   The duration estimates that you complete in schedule planning help you
       define how long the project will take to complete. The work effort estimates that
       you obtain in cost planning are used to define how much the project will cost.



     The final piece of data you need for a bottom-up estimate is the rate for each resource.

     Rates for labor and leased equipment are typically calculated on an hourly or daily
     rate, while the purchase of materials or equipment will generally have a fixed price.

     Deciding the correct rate to use for cost estimates can be tricky. For materials or
     equipment, the current cost of a similar item is probably as accurate as you can get.
     The largest cost for many projects is the human resource or labor cost. The actual rate
     that someone will be paid to perform work, even within the same job title, can fluctuate
     based on education and experience level. If you’re procuring contract resources, you’ll

     get a rate sheet that describes the rates for a given job title and the resource’s travel
     rates if they’re coming from out of town.

     Table 7.1 shows the work effort and rate assigned for each of the resources in a sample
     project.

     TABLE 7.1 Sample project resource rates


                                 Task Resource             Work Effort Rate

                                 4.1.1 Tech writer 20 hours                    $30/hr

                                 4.1.2 Programmer 100 hours                    $150/hr
                                 4.1.3 Server              Fixed rate          $100,000

                                 4.1.4 Testers             60 hours            $80/hr

                                 4.1.5 Programmer 200 hours                    $150/hr

                                 4.1.6 Marketing           30 hours            $60/hr




                                                            198
   193   194   195   196   197   198   199   200   201   202   203