Page 193 - Project+
P. 193

A.  Project status meeting


         B.  Kickoff meeting

         C.  Project introductory meeting

         D.  Steering-committee meeting

    14.  The project sponsor will approve the final deliverables of the project. On a RACI
         chart, how would this be designated?

         A.  R

         B.  I

         C.  A

         D.  C

    15.  Your team is working well together. They understand their roles on the project,

         perform the work with the best effort possible, and really enjoy working with one
         another. A new team member will be introduced next week who is well respected by
         the current team. Which of the following is true regarding this situation? Choose
         two.

         A.  The team is currently in the performing stage of team development.

         B.  Once the new team member is introduced, the team will revert to the forming

              stage of team development.

         C.  The team is currently in the performing stage of team development and will stay
              in performing because they know the new team member.

         D.  Once the new team member is introduced, the team will revert to the norming
              stage of team development.

         E.  The team is currently in the performing stage of team development and will
              revert to the storming stage of team development because they know the new
              team member.

    16.  Of the situations listed, for which would team-building efforts have the greatest

         impact? Choose three.

         A.  Schedule changes

         B.  Organizational changes

         C.  Personality clashes

         D.  Budget changes

         E.  Staff changes

         F.  Organizational changes

    17.  All the following are elements of the project kickoff meeting except for which one?



                                                            193
   188   189   190   191   192   193   194   195   196   197   198