Page 194 - Project+
P. 194
A. Introductions
B. Overview of goals and objectives
C. High-level budget overview
D. Roles and responsibilities overview
E. WBS overview
F. Stakeholder expectations
18. Which conflict-resolution technique is known as win-lose?
A. Smoothing
B. Avoiding
C. Confronting
D. Forcing
19. Resources who are awaiting new assignments between projects are costly to an
organization and typically reside in a projectized organizational structure. Which of
the following does this describe?
A. Overallocated resources
B. Benched resources
C. In-house resources
D. Remote resources
20. One way you are presenting the work of the project is by listing the departments
responsible for the work along with the work packages they’re assigned to. What
type of chart is this?
A. RBS
B. Project organization chart
C. OBS
D. Organization chart
194