Page 29 - Project+
P. 29
Assessment Test
1. Which of these terms describes a critical path task?
A. Hammock
B. Zero float
C. Critical task
D. Mandatory task
2. Resource management concepts include several categories of resources. All of the
following are a type of resource except for which one?
A. Shared resource
B. Remote and in-house
C. Dedicated resources
D. Benched resources
3. This tool is often used in the vendor selection process to pick a winning bidder.
A. Weighted scoring model
B. Bidder conference
C. RFQ
D. SOW
4. From the following list of options, select three of the five common stages of
development that project teams progress through. Choose three.
A. Forming
B. Acquiring
C. Storming
D. Adjourning
E. Negotiating
F. Norming
G. Compromising
5. In this organizational structure, you report to the director of project management,
and your team members report to their areas of responsibility (accounting, human
resources, and IT). You will have complete control of the project team members’
29