C.  Agile


         D.  Waterfall

   20.  This is often added to the project schedule to determine whether the work is
         correct.

         A.  Approval gate

         B.  Quality gate

         C.  Milestone gate

         D.  Governance gate

    21.  This is the final, approved version of the project schedule. All of the following are
         true regarding this term except for which of the following?


         A.  It will prevent future schedule risk.

         B.  It’s approved by the stakeholders, sponsor, and functional managers.

         C.  It’s used to monitor project progress throughout the remainder of the project.

         D.  This describes a schedule baseline.

   22.  A well-written change control process should include which of the following
         components? Choose two.

         A.  A description of the type of change requested

         B.  The amount of time the change will take to implement

         C.  The cost of the change

         D.  How to update the affected project planning documents


         E.  The stages at which changes are accepted

   23.  Which cost-estimating technique relies on estimating work packages and then
         rolling up these estimates to come up with a total cost estimate?

         A.  Top-down

         B.  Parametric

         C.  Bottom-up

         D.  Analogous

   24.  In project management, the process of taking high-level project requirements and
         breaking them down into the tasks that will generate the deliverables is called

         what?

         A.  Analyzing

         B.  Decomposing