Page 37 - Project+
P. 37

D.  Business acquisition


   40.  What are the two types of charts that you might utilize to display the project
         schedule? Choose two.

         A.  Run chart

         B.  Gantt chart

         C.  Milestone chart

         D.  CPM

         E.  Histogram

    41.  All of the following describe types of project endings except for which one?

         A.  Integration

         B.  Starvation


         C.  Addition

         D.  Extinction

         E.  Attrition

   42.  Demonstrating competency, respect, honesty, integrity, openness, and doing what
         you say you’ll do is an example of which of the following?

         A.  Team building

         B.  Managing team resources

         C.  Demonstrating leadership skills

         D.  Trust building

   43.  This is the approved, expected cost of the project.


         A.  Expenditure budget

         B.  Expenditure baseline

         C.  Cost budget

         D.  Cost baseline

   44.  “Install an Interactive Voice Response System that will increase customer response
         time by an average of 15 seconds and decrease the number of customer service
         interactions by 30 percent” is an example of which of the following elements of the
         project charter?


         A.  High-level requirements

         B.  Goals and objectives

         C.  Project description



                                                             37
   32   33   34   35   36   37   38   39   40   41   42