D. Business acquisition
40. What are the two types of charts that you might utilize to display the project
schedule? Choose two.
A. Run chart
B. Gantt chart
C. Milestone chart
D. CPM
E. Histogram
41. All of the following describe types of project endings except for which one?
A. Integration
B. Starvation
C. Addition
D. Extinction
E. Attrition
42. Demonstrating competency, respect, honesty, integrity, openness, and doing what
you say you’ll do is an example of which of the following?
A. Team building
B. Managing team resources
C. Demonstrating leadership skills
D. Trust building
43. This is the approved, expected cost of the project.
A. Expenditure budget
B. Expenditure baseline
C. Cost budget
D. Cost baseline
44. “Install an Interactive Voice Response System that will increase customer response
time by an average of 15 seconds and decrease the number of customer service
interactions by 30 percent” is an example of which of the following elements of the
project charter?
A. High-level requirements
B. Goals and objectives
C. Project description