30.  Risk analysis includes all of the following except for which one?


         A.  Identifying risk

         B.  Determining a risk response plan

         C.  Determining an order-of-magnitude estimate for responses

         D.  Determining probability and impact and assigning a risk score

    31.  Which of the following are project management phases? Choose three.

         A.  Scheduling

         B.  Planning

         C.  Executing

         D.  Communicating


         E.  Documenting
         F.  Budgeting


         G.  Closing

   32.  When taking over an incomplete project, what item should be of most interest to
         the new project manager?

         A.  Project concept statement

         B.  Project charter

         C.  Project scope statement

         D.  Project plan

   33.  This chart or diagram is a type of histogram that rank-orders data by frequency
         over time.


         A.  Run chart

         B.  Scatter diagram

         C.  Fishbone diagram

         D.  Pareto chart

   34.  These performance measurements are defined when you create the project
         management plan and are monitored and tracked during the Monitoring and
         Controlling phase to determine whether the project is meeting its goals.

         A.  SPI

         B.  Balanced score card


         C.  CPI

         D.  KPI