         D.  Documenting

   25.  Who is responsible for assembling the project’s team members?

         A.  Project sponsor

         B.  Project stakeholders

         C.  Project customer

         D.  Project manager

   26.  All of the following represent a category of contract most commonly used in
         procurement except for which one?

         A.  Time-and-materials

         B.  Cost-reimbursable


         C.  Fixed-price

         D.  Requests for proposal

    27.  This is a deliverables-oriented hierarchy that defines the work of the project.

         A.  Scope document

         B.  Work breakdown structure

         C.  Scope management plan

         D.  Project plan

   28.  Your project sponsor has expressed their need to have real-time project
         information at their fingertips. Which of the following is the best way to meet this

         need?

         A.  By creating a project dashboard with scope, cost, and time elements

         B.  By updating the project status report on a daily basis

         C.  By sending an email every morning to the sponsor describing the current project
              status

         D.  By meeting face to face with the sponsor every day to update them on status

   29.  Your project sponsor told you that the due date for the project is a key to its success
         and there is no chance of the date changing. What is this known as?

         A.  A constraint


         B.  An influence

         C.  A deliverable

         D.  A management directive



                                                             34
   29   30   31   32   33   34   35   36   37   38   39