35. What key meeting is held after the project charter is signed and/or at the beginning
of the Executing process?
A. Project kickoff
B. Project review
C. Project overview
D. Project status meeting
36. What is the best way to prevent scope creep?
A. Make sure the requirements are thoroughly defined and documented.
B. Put a statement in the charter that no additions to the project will be allowed
once it’s underway.
C. Alert the sponsor that you will not be taking any change requests after the
project starts.
D. Inform stakeholders when they sign the project scope statement that no changes
will be accepted after the scope statement is published.
37. Which of these statements describes an assumption?
A. Our senior web developer will be available to work on this project.
B. The electrical capacity at the site of the project event may not be adequate.
C. The project’s due date is June 27.
D. There’s a potential for the server administrator to receive a promotion during
the course of this project.
38. Your subject-matter expert tells you that her most likely estimate to complete her
task is 40 hours. The task starts on Thursday, January 20, at 8 a.m. The team works
8-hour days, and they do not work weekends. Which day will the task end?
A. January 24
B. January 25
C. January 27
D. January 26
39. You are working for an organization and just learned that another organization
with more power and influence is taking over your organization at the first of the
year. What does this describe?
A. Business merger
B. Business demerger
C. Business venture