collaborative platform for team members and stakeholders to review and update
certain documents. You could use all of the following knowledge management tools
to accomplish this except which one?
A. Wiki pages
B. Intranet site
C. Dashboards
D. Collaboration software
2. You have just left a meeting with the project sponsor where you were advised that
your project has been canceled because of budget cuts. You have called the project
team together to fill them in and to review the remaining activities to close out the
project. Several of your team members question the benefit of doing a lessons
learned review on a project that has been canceled. What should your response be?
A. Advise the team that part of the review time will be spent on documenting the
failure of the lack of clear requirements from the customer.
B. Tell the team they need to do this to be able to stay on the project payroll
another week while they look for a new assignment.
C. Inform the team that a final report is a requirement from the PMO, regardless of
how the project ends.
D. Explain that there is value both to the team and for future projects in analyzing
the phases of the project that have been completed to date to document what
went right, what went wrong, and what you would change.
3. You have just left a meeting with the project sponsor where you were advised that
your project has been canceled because of budget cuts. You have called the project
team together to fill them in and to review the remaining activities to close out the
project. Which of the following describes the type of project ending this project
experienced?
A. Extinction
B. Starvation
C. Addition
D. Integration
4. Which of the following measurement tools are used to measure operational or
performance goals for systems?
A. KPIs
B. KPPs
C. Balanced score card