D. Run chart
5. Which of the following is the “best” type of project ending?
A. Extinction
B. Addition
C. Integration
D. Starvation
6. What is the primary purpose of a formal sign-off at the conclusion of the project
work?
A. The sign-off allows the project manager to start a new assignment.
B. The sign-off means the project team is no longer accountable for the product of
the project.
C. The sign-off is the trigger for releasing team members back to their functional
organization.
D. The sign-off indicates that the project meets the documented requirements and
the customer has accepted the project deliverables.
7. Which of the following charts is a type of histogram?
A. Scatter diagram
B. Fishbone
C. Pareto chart
D. Run chart
8. What is the focus of the lessons learned report?
A. The report should cover both the positive and negative aspects of the project,
with suggestions for improvement.
B. The report should primarily summarize the results of the project schedule, the
budget, and any approved scope changes.
C. The report should focus on the project deliverables and any issues that were
created by the customer.
D. The report should cover what went well during the project and should
determine which team member or business unit was responsible for failures or
issues.
9. Your project is winding down, and some of your team members are anxious about
their status. What is the best way to deal with their concerns?
A. Explain to the team members that they will be released when the project is
done.