result. Its primary purpose is the customer’s acceptance of the product of the

         project. Team members are released after sign-off, but this isn’t the primary
         purpose of a formal sign-off. Both the project manager and the project team
         members may continue to be involved in the project until all closure activities are
         complete.

     7.  C. A Pareto diagram is a type of histogram that measures the frequency of
         occurrences of data elements in rank-order over time.


     8.  A. Both the successes and failures of a project need to be documented in the lessons
         learned report. Successes will provide blueprints to follow on future projects, and
         failures will alert teams on what to avoid. A good lessons learned document covers
         all aspects of the project from all participants. It should include all project
         information, not just schedule, budget, and changes, and it should never place
         blame for the things that went wrong.

     9.  D. Both team members and functional managers need to know in advance when

         you think a team member will be released. Team members may roll off the project
         at different times, so you need to discuss the release with each team member
         individually.

    10.  C. The fishbone diagram is a cause-and-effect diagram. Brainstorming sessions are
         a great way to construct this chart and determine what causes are impeding your
         results.

    11.  B. Action items generally arise during the status meetings. They should be
         documented in an action item list. They are assigned an identification number, a

         description, and an owner, and their status is recorded and reviewed at status
         meetings. Issues generally impact the project work directly and may impede
         progress or bring about a risk. Action items are usually “to dos” or questions that
         must be answered regarding the project.

    12.  A. Status reports update stakeholders on project progress. The issues log and action
         item list are usually distributed with the status report. Wiki pages are a way to
         distribute the reports. Meeting minutes document what occurred during the

         meeting and what decisions were made, while dashboards are up-to-date, real-time
         information on the status of key project elements.

    13.  D, E. Addition occurs when the project evolves into ongoing operations. Integration
         occurs when the resources on the project are reassigned to other projects or
         activities. When a project fails, is canceled, or otherwise ends before completion,
         the next step is performing a postmortem review.


    14.  B, D. Fishbone diagrams are cause-and-effect diagrams. Scatter diagrams are used
         to determine whether there is a correlation between cause and effect.

    15.  C. The project close report is produced at the end of the project, and it serves as the
         final status report. It summarizes the project goals, costs, schedule, lessons learned,