Page 329 - Project+
P. 329

3.  B. The change control board (CCB) is responsible for reviewing and approving,

         denying, or deferring change requests.

     4.  A. Emergency change request procedures should be documented so that changes
         that must be made on an emergency basis prior to the next CCB meeting can be
         made. All changes should be documented and reported at the next CCB meeting.

     5.  D. After options A–C are conducted, the change request and analysis are given to
         the CCB to make a decision. The appropriate project planning document is not

         updated until the CCB makes a decision regarding the disposition of the change
         request.

     6.  A, D. Determining the constraint that stakeholders think is driving the project will
         help you determine the kinds of trade-offs or alternatives you can propose to lessen
         the effect of the proposed scope change.

     7.  C. The correct action to take in this situation is to submit the change request to the
         CCB. If it is approved, it will require that you rebaseline the schedule to reflect the
         new dates.


     8.  D. Make-or-buy analysis is the technique of determining the cost-effectiveness of
         procuring goods or services outside the organization.

     9.  C. An acquisition gives power to the organization that is taking over. In this
         scenario, your old company has experienced some layoffs and managers from the
         new organization have taken over. This describes an acquisition.

    10.  D. The statement of work (SOW) describes in detail the goods or services you are
         purchasing from outside the organization.


    11.  B. Bidders conferences are usually set up shortly after the RFP is posted and allow
         vendors the opportunity to ask questions about the project.

    12.  A. Weighted scoring models weigh various criteria from the RFP and SOW, which
         allows you to score each vendor on each of the criteria and determine an overall
         score for each vendor.

    13.  D. Cost-reimbursable contracts are the riskiest for buyers, since the buyer is
         responsible for reimbursing the seller on the costs of producing the goods or
         services.


    14.  A. Time and materials contracts are a cross between fixed-price and cost-
         reimbursable contracts. They assign a unit rate for work, but the total cost isn’t
         known until the work is complete.

    15.  B. The project management plan serves as the baseline for project progress and is
         used throughout the Executing and Monitoring and Controlling phases to
         determine whether the project is on track. It is used to help evaluate changes
         against the original goals and objectives of the project and serves as a

         communication tool.



                                                            329
   324   325   326   327   328   329   330   331   332   333   334