Page 88 - Project+
P. 88

project baseline


         project coordinator

         project management office (PMO)

         project team

         scheduler

         sponsor

         stakeholder



     Review Questions


     1.  You have identified all the key stakeholders on the project. You’ve listed their
         names, departments, interests in the project, and level of influence. What have you

         created? Choose two.

         A.  A project request

         B.  A stakeholder matrix

         C.  An artifact

         D.  A business case

         E.  A high-level scope definition

     2.  This person is responsible for authorizing the project to begin and for signing the
         project charter.

         A.  Project sponsor


         B.  Executive in the organization who requested the project

         C.  Project champion

         D.  Project manager

     3.  This team member assists the project manager with administrative functions.

         A.  Project management office

         B.  Project scheduler

         C.  Project coordinator

         D.  Project sponsor

     4.  A key responsibility of the project manager includes informing this person of
         changes, status, conflicts, and issues on the project.


         A.  The project requestor

         B.  The project sponsor


                                                            88
   83   84   85   86   87   88   89   90   91   92   93