Review Questions
1. You have identified all the key stakeholders on the project. You’ve listed their
names, departments, interests in the project, and level of influence. What have you
created? Choose two.
A. A project request
B. A stakeholder matrix
C. An artifact
D. A business case
E. A high-level scope definition
2. This person is responsible for authorizing the project to begin and for signing the
project charter.
A. Project sponsor
B. Executive in the organization who requested the project
C. Project champion
D. Project manager
3. This team member assists the project manager with administrative functions.
A. Project management office
B. Project scheduler
C. Project coordinator
D. Project sponsor
4. A key responsibility of the project manager includes informing this person of
changes, status, conflicts, and issues on the project.
A. The project requestor
B. The project sponsor