A. Sponsor
B. Customer
C. Client
D. B and C
E. All of the above
15. Project team members are responsible for several aspects of the project. Choose
three.
A. Contribute deliverables according to the schedule
B. Set standards and practices
C. Cross-functional coordination
D. Provide input and requirements
E. Estimate task durations
F. Estimate costs
16. Rahul is a key resource for your project. You’ve worked with him on past projects
and have identified him as one of the team members for this project. Some of
Rahul’s duties will include reporting on schedule performance, obtaining task
status from team members, communicating timelines, and communicating changes
to timelines. What is Rahul’s role on this project?
A. Project scheduler
B. Project manager
C. Project coordinator
D. PMO team member
17. Your project team members and key stakeholders are confused about the project
you are all working on. What is the most compelling reason for this?
A. The problem or need generating the project request was not defined.
B. The project sponsor has not signed the project request authorizing it to begin.
C. The business case is not well documented.
D. The project team members don’t understand their roles and responsibilities.
18. The governance processes for project management are well established in your
organization. Who established these processes?
A. Project team
B. Project manager