Page 92 - Project+
P. 92
C. Sponsor
D. PMO
19. This component of the project request describes the project objectives, the high-
level deliverables, and the reason for the project.
A. Project request justification
B. High-level deliverables definition
C. High-level scope definition
D. High-level goals and objectives definition
20. Which of the following are true regarding the project baseline? Choose three.
A. The project baseline is approved by the project manager.
B. The project baseline includes the approved project scope.
C. The project baseline includes the approved business justification.
D. The project baseline includes the approved project quality plan.
E. The project baseline includes the approved project request.
F. The project baseline includes the approved project schedule.
G. The project baseline is approved by the project sponsor.